Owllegal
  • Home
  • Specialisms
    • Alternative Dispute Resolution
    • Commercial
    • Construction
    • Contract
    • Corporate
    • Employment
  • Blog
  • Contact
  • Search
  • Menu Menu
  • LinkedIn
  • Twitter
  • Facebook
  • Rss

Extensions Of Time

Contracts
Extensions of Time

There are three key aspects to a building or engineering contract in connection with the timing of that project:

  • The date for completion
  • The mechanism for changing (extending) the date for completion
  • The consequences for the parties of a failure to meet the date for completion

At the outset, particularly if a project includes works by a number of different contractors, the parties must agree a clear programme or programmes setting out when the different work packages should commence and complete. Without a clear programme, they will not be able to manage the project effectively and prevent delay or allocate the consequences of any delay.

Most building contracts and engineering contain express provision for completion of the works by a certain date. Even in the case of the simplest construction project, it is usually one of the few things that the parties make sure to agree on during their negotiations.

If the contract does not include a contractual date for completion, this does not mean that the contractor can take as much time as it likes. In these circumstances, Section 14 of the Supply of Goods and Services Act 1982 implies a term requiring the contractor to complete its works within a reasonable time:

“Where, under a contract for the supply of a service by a supplier acting in the course of business, the time for the service to be carried out is not fixed by the contract, left to be fixed in a manner agreed by the contract or determined by the course of dealing between the parties, there is an implied term that the supplier will carry out the service within a reasonable time…”

What is “reasonable” is a question of fact in any given case. Delays will often occur on a project that are not the contractor’s fault or responsibility. For example, a delay may arise because the employer is unable to give the contractor possession of the site on time, or because the employer has instructed the contractor to carry out additional works (as a variation to the original scope of works.

If a delay event occurs that is the employer’s fault and the contract does not make provision for that delay, the original completion date falls away and time is put “at large”. This means the contractor is under an obligation to complete the works within a reasonable time.

Time at large results from the application of the “prevention principle”, which provides that no party may require the other to comply with a contractual obligation in circumstances where that party has itself prevented such compliance. If the employer has prevented the contractor from carrying out the works “on time” according to the original contractual completion date (and the contract does not provide for how that delay is dealt with), the employer cannot insist that the contractor meets the original date for completion.

There are two types of delay for which a contractor may be able to claim an extension of time: (a) Delay the employer caused and (b) Other delays that are not the contractor’s responsibility under the contract. The employer may have specific notification requirements, but the employer and/or the contract administrator may suspend or waive compliance with the contract’s notification requirements. They may do this expressly. Alternatively, a court may find that compliance with a contract term has been waived by silence or through the conduct of the parties. However, in practice, the parties rarely waive these notice requirements.

It is vital that the Contractor, knows the conditions precedent to make extension of time claims, under the contract, and that they adhere to these procedures, or they face the potential of losing the right to claim. Early legal advice is essential!

Acknowledgement: Thomson Reuters online resource Practical Law

NOT LEGAL ADVICE: Information provided in this Blog, is for information purposes only. It is not and should not be taken as legal advice. You should not relay on or take or fail to take any action based upon this information. Never disregard taking legal advice or delay in seeking legal advice because of something you have read in this blog, or on this website. Ian Randall is an Attorney & Counsellor at Law (NY), with 25 years of Corporate and Commercial experience in several jurisdictions. To see how Owllegal could help you, please visit; www.owllegal.org or email Ian Directly, his email address is ian@owllegal.org.

by Ian Randall
Share this entry
  • Share on Facebook
  • Share on Twitter
  • Share on WhatsApp
  • Share on Pinterest
  • Share on LinkedIn
  • Share on Reddit
  • Share by Mail
https://www.owllegal.org/wp-content/uploads/2020/01/extensions-time.jpg 800 1200 Ian Randall https://www.owllegal.org/wp-content/uploads/2017/12/owllegal-logo-light-header.png Ian Randall2020-01-03 18:00:272020-01-05 18:05:55Extensions Of Time

Latest Blogs

  • Legal AdviceWho Can Give Business Law Advice?January 5, 2020 - 7:43 pm
  • Director DutiesDirectors of Companies in Financial DifficultiesJanuary 5, 2020 - 5:57 pm
  • MeetingBoard MeetingsJanuary 5, 2020 - 3:57 pm
  • DirectorActing As A De Facto Or Shadow DirectorJanuary 5, 2020 - 3:43 pm
  • Buying a CompanyOverview of Buying a Private CompanyJanuary 3, 2020 - 6:14 pm
  • Extensions of TimeVariationJanuary 2, 2020 - 6:58 pm
  • Director DutiesServed With A Winding Up PetitionJanuary 2, 2020 - 6:26 pm
  • Director DutiesDirectors’ general duties under the Companies Act 2006January 2, 2020 - 5:09 pm
  • MeetingBoardroom and Shareholder DisputesJanuary 1, 2020 - 4:38 pm

Owllegal Limited

6 Windsor Road
Normoss
Blackpool
FY3 7SQ

Tel: +44 7399 055 548

Email: info@owllegal.org

Ian Randall

Results driven Corporate and Commercial Lawyer with 29+ years of experience ensuring the legality of Corporate and Commercial transactions. Adept at drafting corporate and commercial documents, reviewing, disputing, and advising on Commercial and Corporate matters. Clear ADR: Accredited Civil and Commercial Mediator and Alternative Dispute Resolution Specialist.

Honours Degree in Law and a master’s degree in Employment Law and Practice from the University of Central Lancashire.

A member of the New York State Bar in Good Standing.

Owllegal

ICO Data Protection Registration Numbers

Owllegal               ZA 535 767
Ian Randall          ZA 744 861

© Copyright 2022 - Owllegal Limited.
  • LinkedIn
  • Twitter
  • Facebook
  • Rss
  • Privacy Policy
  • Website Disclaimer
  • Required Disclosures
VariationExtensions of TimeBuying a CompanyOverview of Buying a Private Company
Scroll to top

This site uses cookies. By continuing to browse the site, you are agreeing to our use of cookies.

Accept settingsHide notification onlySettings

Cookie and Privacy Settings



How we use cookies

We may request cookies to be set on your device. We use cookies to let us know when you visit our websites, how you interact with us, to enrich your user experience, and to customize your relationship with our website.

Click on the different category headings to find out more. You can also change some of your preferences. Note that blocking some types of cookies may impact your experience on our websites and the services we are able to offer.

Essential Website Cookies

These cookies are strictly necessary to provide you with services available through our website and to use some of its features.

Because these cookies are strictly necessary to deliver the website, refusing them will have impact how our site functions. You always can block or delete cookies by changing your browser settings and force blocking all cookies on this website. But this will always prompt you to accept/refuse cookies when revisiting our site.

We fully respect if you want to refuse cookies but to avoid asking you again and again kindly allow us to store a cookie for that. You are free to opt out any time or opt in for other cookies to get a better experience. If you refuse cookies we will remove all set cookies in our domain.

We provide you with a list of stored cookies on your computer in our domain so you can check what we stored. Due to security reasons we are not able to show or modify cookies from other domains. You can check these in your browser security settings.

Google Analytics Cookies

These cookies collect information that is used either in aggregate form to help us understand how our website is being used or how effective our marketing campaigns are, or to help us customize our website and application for you in order to enhance your experience.

If you do not want that we track your visit to our site you can disable tracking in your browser here:

Other external services

We also use different external services like Google Webfonts, Google Maps, and external Video providers. Since these providers may collect personal data like your IP address we allow you to block them here. Please be aware that this might heavily reduce the functionality and appearance of our site. Changes will take effect once you reload the page.

Google Webfont Settings:

Google Map Settings:

Google reCaptcha Settings:

Vimeo and Youtube video embeds:

Other cookies

The following cookies are also needed - You can choose if you want to allow them:

Accept settingsHide notification only